11. ENVIRONMENTAL
OUTCOMES and Conclusions
11.2 Summary of Key Environmental Outcomes
11.3 Principal Findings of the EIA Study
11.4 Environmental Monitoring and Audit
LIST OF TABLES
Table 11-1 Summary of Key Environmental Outcomes / Benefits
·
Air Quality Impact
·
Noise Impact
·
Water Quality Impact
·
Waste Management and Land Contamination Impact
·
Landscape and Visual Impact
·
Landfill Gas Hazard
·
Impact on Cultural Heritage
Air Quality
· Implementing control measures as stipulated in the Air Pollution Control (Construction Dust) Regulation and good site practise to minimise dust generation.
· The on road traffic speed would be resumed to the design speed limit instead of idling during rush hours. As a result, the overall vehicular emission would likely be reduced in the vicinity area in the future.
Noise
· Recommended mitigation measures during construction phase include: adopting quiet construction plant, movable noise barriers, noise jackets, mufflers, limiting the number of plants operated concurrently as well as good site practices. As a result, the construction noise impact is controlled as minimal.
· Direct noise mitigation measure (DNMM) including vertical noise barrier, cantilevered noise barriers and low noise road surfacing were recommended.
· With the implementation of DNMM, traffic noise impact due to DP road would comply with noise criteria.
Water Quality
· Implementation of good site practices as stipulated in ProPECC Note PN 1/94 to control and minimise site runoff arising from general construction activities associated with the construction of the Project.
· Application of discharge licence for discharge of effluent from the construction site under the WPCO while discharge quality must meet the requirements specified in the discharge licence.
· Treatment of all run-off and wastewater generated from the works areas to satisfy all the standards listed in the Technical Memorandum under WPCO.
· Provision of minimum distance of 100m between the discharge points of construction site effluent and the existing seawater intakes.
· Use of treated effluent for other on-site activities such as dust suppression, wheel washing and general cleaning etc., to minimise water consumption and reduce the effluent discharge volume.
· Provision of properly maintained and regularly cleaned surface runoff collection system to ensure good service condition.
Waste Management and Land Contamination
· With the implementation of the proposed waste reduction, management and mitigation measures and practices associated with handling, transportation and disposal of the identified wastes arising from the Project, no adverse environmental impacts would be anticipated.
Landscape and Visual
“Construction Phase”
· Replanting of disturbed planting areas with shrubs planting will be undertaken at the earliest possible stage of the construction phase.
· Night-time lighting glare will be controlled to prevent light spillage.
· Decorative screen hoarding will be erected.
· All disturbed landscape areas during construction will be restored like-to-like following the completion of the construction phase.
“Operation Phase”
· The carriageway design and associated noise barriers will incorporate design features as part of mitigation measures including choices of material, colour and shape.
· Roadside and amenity planting will utilise flowering and colourful foliage shrubs species in creating a more pleasant landscape network in the area. Large shrubs will be planted to create visual buffers of the supporting columns.
· Enhancement of streetscape using coloured paving materials to tie with the paving theme of Kwai Chung Area.
Landfill Gas
· LFG hazard assessment is considered not necessary as the proposed project does not fall within the 250m Consultation Zone of the closed restored Gin Drinkers Bay Landfill. As such, no mitigation measures have been provided for LFG issue.
Cultural Heritage
· No adverse built heritage impact associated with the Project during both construction and operation phases would be anticipated. Therefore, no mitigation measures for cultural heritage would be required.
· Construction dust and noise impact on air and noise sensitive receivers within the assessment areas have been minimised and mitigated to acceptable levels.
· No adverse air quality impact due to the Project is anticipated during operation phase.
· Approximately 50,000 residential populations within the operational air quality assessment area will be environmental benefitted.
· About 2,900 residential, classrooms and other sensitive elements have been assessed under 300m study area if noise impact assessment. With implementation of proposed mitigation measures, no exceedance of noise criteria due to DP roads and 18 representative NSRs would be protected while 85 residential dwellings would be benefitted.
· Approximately 23,500m2 of construction area would be protected during construction phase. About 4,200m2 of additional road area would be protected during operation phase. In addition, one flushing water intake, two cooling water intake and one typhoon shelter within 300m from the project site would be protected during both construction and operation phases.
·
Air quality would slightly improve due to the relieving of traffic
congestion on Kwai Chung Road in future.
·
The proposed flyover is relatively farther away from the nearby NSRs so
that noise impact to the existing NSRs would be minimised.
·
The site boundary is minimised so that it would not fall into 250m
consultation zone of LFG hazard assessment.
·
Excavated marine sediment would be treated and reused on-site to avoid
the need for off-site disposal.
·
Reuse of inert C&D materials on-site as far as practicable to
minimise amount of off-site disposal.
·
Impacts on the adjacent landscape including LRs, LCAs and VSRs would be
minimised by appropriate landscape and visual appearance designs.
Table 11-1 Summary of Key Environmental Outcomes / Benefits
Area/Issue |
Environmental Outcomes /
Benefits and Mitigation Measures |
The Project |
Requirements: Construction
of a new flyover and relocation of a footbridge are proposed including: • Introduce an additional
southbound lane (a separated viaduct) on TWR and connect to the existing lane
on the west side of KCR with design speed of 70 km/hr • Associated works in the
following areas have been identified: (i) Existing footbridge NF303 is to be
demolished and be re-provided; (ii) Existing
Public Works Regional Laboratory will be affected; (iii) Existing
drainage reserve zone positioned alongside TWR will be affected; (iv) Existing
bus stop outside subway NS10A is to be relocated; and (v) Minor modification to the existing Kwai
Chung Road involves removal of the existing planter, breaking and reinstating
Kwai Chung Road with the new road marking. Benefits: • A section of the SB carriageway
of TWR between KT I/C and KCR predicted would be deteriorate due to
congestion occurs during peak hours in the future years, a flyover is
proposed to improve the road section to cope with the future traffic growth
by directing traffic flow from fast lane of SB TWR to merge the fast lane of
SB KCR • The proposed new flyover would
divert some of the on-road traffic away from the nearby noise sensitive
receivers at Lai King Estate, while noise barrier along the new flyover shall
be provided as required. In this
connection, traffic noise impact due to TWR could be slightly relieved with
this Project in place. • With the decrease of V/C ratio
on SB TWR when this Project is in place, local traffic congestion problem
could be resolved. In other words, the
on road traffic speed would be resumed to the design speed limit instead of
idling during rush hours. As a result,
the overall vehicular emission would likely be reduced in the vicinity area
in the future. |
Preferred Option |
Various options considered and
the preferred option as the most environmentally friendly: • Comprising with other 6 alternatives
options, Option 2A is preferable based on various factors including traffic,
engineering, environmental considerations and implementation aspects, etc. • For the proposed scheme, Option
2A is considered the best road improvement option based on the fact that this
scheme will yield the best traffic performance upon its implementation. The additional lane in this scheme is to
occupy one of the segregated lanes of KCR.
From results of traffic survey, there is over one full lane of
capacity to receive this additional lane.
With respect to the compliance on alignment deign standard,
this option is an compliance on all aspects. |
Construction Air Quality |
Impact/Problem: • Potential air quality impacts
are dust nuisance but expected minimal. Key environmental problem
avoided: • Implement the Air Pollution
Control (Construction Dust) Regulation and good site practice. Environmental benefits of
environmental protection measures recommended: • Construction Dust impact would
be minimised. |
Operational Air Quality |
Impact/Problem/Environmental
Benefit: • No exceedance of RSP, FSP as well as NO2 hourly
average concentration criterion is anticipated during operation phase. • Some ASRs would exceed annual average NO2 concentration
limit in AQOs, under both “Without Project” and “With Project” scenarios. • Exceedance of annual NO2 was mainly resulted from the
high background pollutants’ concentrations in this district. Marine emission
rather than vehicular emission is concluded to the be major contributor to
the high background level in most areas, mainly due to the pollutants emitted
from the Kwai Chung Container Terminal nearby. • Comparison study concluded that some environmental benefits would
be contributed by the Project due to the improvement of traffic flow and
vehicles travelling speed after the implementation of the proposed Project. As a result, no adverse air
quality impacts are anticipated due to the Project. |
Construction Noise |
Impact/Problem: • Unmitigated construction noise
levels: 61 to 81 dB(A). Key environmental
problem avoided: • Recommended mitigation measures:
adopting quiet construction plant, movable noise barriers, noise jackets,
mufflers, limiting the number of plants operated concurrently as well as good
site practices. Environmental benefits of
environmental protection measures recommended & Environmentally sensitive
areas protected: • Under the mitigated scenario,
all representative NSRs would be protected to comply with the daytime
construction noise standard as set out in the EIAO-TM except two NSRs would
exceed noise criteria during examination period at some months. The Contractor shall liaise with the school
representative(s) to obtain the examination schedule and avoid noisy construction
activities during school examination period. |
Road Traffic Noise |
Impact/Problem: • Unmitigated noise levels: 55 to
84 dB(A). Key environmental
problem avoided: • Vertical barrier and
cantilevered noise barrier have been provided for the project roads as shown
in Figure 4.4A. Environmental benefits of
environmental protection measures recommended & Environmentally sensitive
areas protected: • Most representative NSRs cannot
comply with the noise limit of 70 dB(A) for residual
use, 65 dB(A) for institutional uses and 55 dB(A) for clinic due to high
volume flow of existing road networks. • For the affected NSRs with
residual impact, the noise contributions from the DP road to
the overall noise levels would be less than 1.0 dB(A) and the DP road noise
level would be below the relevant noise criteria, although the overall noise
level would still exceed the relevant noise criteria. • Eligibility test shows that all
the NSRs are not eligible for provision of noise insulation works. No further noise mitigation measurement is
required |
Construction Water Quality |
Impact/Problem: • General construction activities
associated with the construction of the Project could lead to site runoff. Key environmental
problem avoided: • All of the recommended
mitigation measures are implemented and all construction site / work area
discharges comply with the TM-DSS standards.
• Treated
effluent would be used for other on-site activities
such as dust suppression, wheel washing and general cleaning etc., Environmental benefits of environmental
protection measures recommended: • The beneficial uses of the treated effluent would minimise water
consumption and reduce the effluent discharge volume. • No unacceptable residual water
quality impacts are expected during the construction of the proposed works. |
Operational Water Quality |
Impact/Problem: • Adverse water quality impacts
associated with the operation of the Project are not expected at the water
sensitive receivers within the study area with properly designed and maintained surface
runoff collection system including silt traps and road gullies along the road
alignment. Thus, there will be no residual impact
associated with the operation of the Project. |
Waste Management and Land Contamination |
Impact/Problem: • The Project is likely to result
in the generation of a variety of wastes and require the management and
disposal of C&D material, C&D waste, marine
sediment, chemical waste and general
refuse. • The Public Works Regional
Laboratory of Tsuen Wan (Laboratory) has been identified as a chemical waste
producer, which is a potential contaminated land use within the project
boundary. The allocatee shall be responsible for
the land contamination assessment of the Laboratory Site and ensure the
Laboratory Site is free from contamination at the expiry of allocation and
therefore any land contamination concern arising from past activities would
have been remediated prior to the construction of the works. Environmental benefits of
environmental protection measures recommended: • With the implementation of the
proposed waste reduction, management and mitigation measures and practices
associated with handling, transportation and disposal of the identified
wastes arising from the Project, no adverse environmental impacts would be anticipated. |
Landscape and Visual (Construction Phase) |
Impact/Problem: • Landscape Resources: -
LR2 Tree Planting at Kwai Chung Road Interchange Area would expect to
experience moderately adverse
impacts • Landscape Character Area: -
LCA 3
Residential at Lower level of Lai King Hill and LCA6 Kwai Chung Road Interchange would expect to receive slightly adverse impact. • Visual Sensitive Receivers: -
R5 Lai King Estate North; O5 Lai King Catholic Secondary School would
expect to receive moderately adverse
impact. -
R5A Lai
King Estate South; R6 Yin Lai Court; R7 Highland
Park; O4 Polyclinic & Special Educational Services; O6 Ever Gain Plaza; O8 Lingnan Dr. Chung
Wing Kwong Memorial Secondary School; O10 Lai King Assessment Centre; L1 Kwai
Shun Street playground; T1 Open Storage Area Car Park
Users; T2 Pedestrians Travelling on Street Level Under Kwai Chung Road
Interchange; T3 Commuters on Tsuen Wan Road/Kwai Chung Road, T4
Commuters at Lai King Bus Terminus and T5 Commuters on MTR would expect to receive slightly adverse impacts. • All other LRs, LCAs and VSRs
would experience insubstantial impacts. Key environmental
problem avoided: • CP1 – The construction site is carefully designed to minimise impact on adjacent
landscape. • CP2 – Replanting of disturbed planting areas with shrubs planting would be undertaken as earliest possible
during the construction phase. |
Landscape and Visual (Operation Phase – By Year 10) |
Key environmental
problem avoided: • OP1 – The proposed carriageway
structures will incorporate design features as part of
mitigation measures. • OP2 – The associated noise barrier should
incorporate different means of mitigation measures for the associated noise
barrier structures to reduce potential impacts. • OP3 – Roadside and amenity planting will be utilised throughout the
site. • OP4 – The landscape proposal should consider introducing coloured paved
materials to tie with the paving theme of Kwai Chung area. Environmental benefits of environmental
protection measures recommended: • Landscape Character Area: -
LCA6 Kwai Chung Road Interchange would expect to receive slightly beneficial impact. • Visual Sensitive Receivers: -
T1 Open Storage Area Car Park Users; T2 Pedestrians Travelling on
Street Level under Kwai Chung Road
Interchange; would expect to receive slightly beneficial impact. • All other LRs, LCAs and VSRs
would experience insubstantial impacts. |
Landfill Gas Hazard |
Impact/Problem: • As the work area of the Project does
not fall within 250m consultation zone of the restored Gin Drinkers Bay
Landfill, LFG hazard assessment is considered not necessary. No LFG hazard impact is anticipated. |
Cultural Heritage |
Impact/Problem: • As no cultural heritage resource
was identified within the Assessment Area of the Project, no impacts to
cultural heritage are expected to be anticipated during both construction and
operational phases of the Project. |
Construction Phase
Operation Phase
Construction Phase
Operation Phase
Construction Phase
Operation Phase